June 11, 2004
At long last, it's
a go for Jericho
Nunavut's first diamond
mine gets green light from Ottawa
JIM
BELL
The minister of Indian
and northern Affairs, Andy Mitchell, has accepted the Nunavut Impact Review
Board's advice and said yes to the Tahera Corp.'s Jericho diamond mine, Canada's
fourth and Nunavut's first, creating scores of possible job openings for Kitikmeot
residents.
"It certainly paves
the way for us to get on to that next stage, which is getting the permits in
place, the water permit and the land leases," said Greg Missal, Tahera's
vice president for Nunavut affairs.
Missal said the company
hopes to start shipping construction materials to Jericho via the winter road
from Yellowknife in February. After about a year of construction work, Tahera
hopes to dig up diamonds by late 2005 or early 2006 for sale to an as-yet-unspecified
buyer.
The company estimates the
mine will operate for eight years, unless its exploration efforts turn up new,
commercially viable kimberlite deposits.
This week, Tahera signed
a deal with De Beers Canada Exploration Inc., under which Tahera will explore
for diamonds on De Beers' land next door to Jericho. Tahera will earn itself
a 50 per cent share of any diamonds produced from the area - if its four promising
kimberlites turn out to hold commercial quantities of diamonds.
Under the recent Inuit
impact and benefits agreement between Tahera and the Kitikmeot Inuit Association,
Kitikmeot Inuit could get up to 60 per cent of Jericho's mine construction and
production jobs - within five years of the mine's startup.
That would include at least
some of the 45 to 120 people who will be needed to construct the mine and an
on-site diamond processing plant. Between 48 and 116 people will be needed for
three years to work on open-pit mining, while another 48 people will work for
two years in underground mining.
The processing plant, to
be built and managed by a South African company called Dowding, Reynard and
Associates, will employ about 40 people for eight years.
Missal said the federal
government's approval of the project will now make it easier for the company
to find investors willing to put up the $53 million that Tahera needs to pay
for the Jericho mine's startup costs.
"The financial institutions
are very aware of what federal approval means for a project," Missal said.
They're also still seeking
a buyer for the rough diamonds that Jericho will produce.
Though Tahera's agreement
with the Kitikmeot Inuit Association contains a provision saying that KIA and
Tahera may one day talk about supplying some rough diamonds to a local firm,
Missal said that's not likely to happen soon.
He said that Tahera is
looking for a marketing arrangement where they would sell everything they produce
to one outside buyer.
Nuna Logistics, owned by
the Nunasi Corporation and the Kitikmeot Corporation, is the "preferred"
contractor for the construction project. Nuna Logistics will start by building
a camp, diesel storage, workshop, explosive storage and on-site ice access roads.
Located about 25 km northwest
of the soon-to-expire Lupin gold mine, about 350 km southwest of Cambridge Bay,
the Jericho mine is small when compared with the two giant diamond mines now
operating in the Northwest Territories, Diavik and Ekati, and De Beers' Snap
Lake project north of Yellowknife, which received federal approval June 3.
Diavik, for example, cost
more than $900 million to construct, and is roughly 20 times the size of the
mine proposed by Tahera.
After a lengthy environmental
screening and review, the Nunavut Impact Review Board recommended early last
February that the federal government approve the Jericho mine.
But as time passed, Nunavut
leaders grew impatient with what they perceived to be unnecessary foot-dragging
by federal officials. In May, Premier Paul Okalik wrote to Geoff Regan, minister
of fisheries and oceans, accusing his department of imposing needless delays
in its review of the NIRB's recommendations.
Just last week, Okalik
again accused Ottawa of delaying the project for no valid reason.
Meanwhile, the Inuit of
the Kitikmeot will be looking to their IIBA to protect their social and economic
interests.
Here are a few highlights
from the KIA-Tahera IIBA:
- Tahera will use its
"best efforts" to reach a 60 per cent Inuit employment level by
Year 5 of the project;
- Tahera will post Jericho
job vacancies in all Kitikmeot communities - if no qualified candidates are
identified after a 10-day waiting period, Tahera may hire workers from the
outside;
- Tahera commits to requiring
a mimimum Grade 10 education for entry level jobs, but may adjust entry requirements
for Inuit applicants;
- Two-week-in, two-week
out work rotations will be used during diamond production, and four-week-in,
two-week-out work rotations will be used during exploration, construction
and development;
- All jobs at Jericho
will be open to Inuit with the ability, work skills, experience, and necessary
qualifications - Tahera will consider equivalencies instead of paper qualifications,
where appropriate;
- All employees must submit
to security checks before they're hired, and all employees must obey on-site
security rules similar to those used at other diamond mines.