August 5, 2005
Water, water everywhere...
To understand
Iqaluit's busiest construction season, it helps to follow the wet stuff
JOHN THOMPSON
CLICK
PHOTO TO ENLARGE
The city is
starting work on a new sewage treatment plant to replace the former $7 million
structure that was suppposed to open in 1999, but never worked. (PHOTOS BY JIM
BELL)
|
To understand Iqaluit's busiest construction season, it helps to follow the
wet stuff
Nearly every truck driver on the road wore a hard hat this past civic holiday
in Iqaluit, where, as many government employees snoozed their way through the
morning, backhoe loaders and bulldozers plugged the Ring Road.
Nunavut's capital is in the midst of one of its most ambitious construction
seasons, although many of the changes will occur beneath the ground, out of
sight. From early July to late September, the few months when the temperature
is warm enough for the ground to thaw, the city will spend $10-$13 million dollars.
Much rests on these projects. They're financed by a six-year capital agreement
with the Government of Nunavut, which has agreed to bankroll most expenses,
provided the projects are completed by May 2008. If they're not, the city of
Iqaluit could be left to pay any outstanding bills.
"Big year," says Brad Sokach, the city's outgoing engineer.
CLICK
PHOTO TO ENLARGE
Road-building
crews from Kudlik Construction have been using explosives to blast through rock
at the new Plateau subdivision.
|
To make sense of these changes, it helps to look a bit past the construction
workers, at the burbling brooks that trickle down rocky embankments, through
culverts and eventually, through meandering paths, into Frobisher Bay. For above
all, the story of Iqaluit's expansion is a story about water.
It begins at Lake Geraldine Dam, the city's water reservoir. Recently the city
tenured a $1.2 million contract to drill into the fractured bedrock the dam
rests on and install metal rods to help anchor the structure in place. To keep
pace with a growing population that's expected to outstrip the existing reservoir
in the next three to seven years, the lake's water level will rise by two metres
next year.
Combined with a new treated water storage tank, costing $222,000, this increased
water volume will feed new residential areas, like the Plateau subdivision,
where the first phase of construction is currently underway. Including the water
booster station, that development will cost about $6 million. It's the only
large construction effort not covered by the capital plan agreement with the
GN.
Water will also soon pump into existing homes currently supplied by truck in
Lower Base, where the stench of unearthed petroleum-contaminated soil has caught
the attention of Iqalungmuit during the installation of water and sewage lines.
CLICK
PHOTO TO ENLARGE
Kudlik Construction
is now building roads and installing water and sewage lines to create the first
phase of Iqaluit's new Plateau subdivision, just above the Arctic College building.
|
The lower base utilidor lines will cost about $3 million, half of which was
spent last year. Removing 48 homes in Lower Base from truck service will significantly
cut future service costs.
More piped water also means fewer city trucks on the road - and fewer chances
for fatal accidents involving them, like the ones that occurred several years
ago. More water pressure also reduces the risk posed by fire. When the old Joamie
school went up in flames in 2003, one reason for the building's demise was diminishing
water pressure.
With the flush of a toilet, water leaves homes as sewage. Right now, that sewage
is discharged into the city's smelly and overflowing sewage lagoon.
"A properly designed lagoon should hold sewage for about eight months,"
Sokach said. "Ours does for about 10 days."
New sewage treatment facilities to replace the lagoon are currently being built
inside the old plant, a building finished at a cost of over $7 million - which
never actually worked.
"This will work," Sokach says.
That project will cost $3.2 million for first phase this year, and $5.6 million
the following year, plus engineer's fees.
CLICK
PHOTO TO ENLARGE
For the past
two weeks, a crew working for Tower Arctic dug trenches and installed utilidor
pipes at the upper end of Ben Ell Drive in Iqaluit's Lower Base neighbourhood.
|
What will be done with the sludge the plant will produce is still unclear -
Sokach said it will be either packed in a landfill or used as compost. A study
is currently being done on other northern communities to judge which method
is best for Iqaluit.
The city's under-code sewage lift station will also be upgraded, at a cost
of $1.7 million. Currently it has inadequate wiring and heat, but most importantly,
there's no backup generator, which means when the power fails, sewage trucks
need to be rushed to the station to prevent raw sewage from spilling into the
bay, which is exactly what happened in 2000.
Even plans to pave sections of road leading to Apex and Tundra Valley with
a technique called chip-sealing hinge on water, since the technology depends
on dry weather and warm temperatures. About $650,000 has been set aside for
that project.
Lesser projects include $300,000 towards crossing the waters, with repair work
done to Iqaluit's three bridges.
And $80,000 will be spent on the final stage of containing petroleum-contaminated
waters inside the old North 40 metal dump, which continues to serve as the city's
source of gravel.