August 2, 2002
Major repairs needed for
sewage plant, engineers report shows
City must pay almost
$4 million, on top of the $7 million already paid, to get plant running
DENISE
RIDEOUT
Its going to cost
the City of Iqaluit $550,000 to finish repairs to its sewage treatment plant,
which was supposed to be up and running two years ago, and another $3.3 million
to increase its capacity to handle all the citys waste.
The plant, which is intended
to replace Iqaluits sewage lagoon, has been flawed from the beginning.
In 2000 when the plant
was built, engineers discovered leaks in the walls of the concrete tanks. Following
that, work on the sewage treatment plant stopped cold.
Since then, city council
has been struggling to find a way to get the plant, which comes with a $7-million
price tag, finally working.
This January, council commissioned
engineers from Earth Tech Inc. of B.C. to inspect the sewage treatment plant
to spell out how much work is left to complete it and how much it will
cost the city every year to run it.
The engineers report,
released this week, shows there are some defects in the plants design,
major improvements are needed and it doesnt meet all the safety requirements.
The floor of the electrical
room is sagging and may cause drainage problems, some of the electrical systems
dont meet Canadian electrical codes and better ventilation should be installed,
the engineers say.
But the flaws come as no
surprise to Iqaluits mayor. "I think, from councils perspective,
those defects are not that important because we knew it wasnt working,"
John Matthews said.
On top of that, it turns
out that running the facility will cost more than council anticipated.
"Six hundred thousand
dollars is just too onerous on the city," Matthews said.
But the key, the mayor
says, is the significant discovery that the plant might not have the capacity
to treat all of the sewage that is generated in Iqaluit.
"The plant wasnt
designed to meet the needs of Iqaluit at its peak times, especially given its
rapid growth over the past few years," Matthews explained.
The plant was built to
handle 1,800 cubic metres of waste a day, but the current population is producing
about 2,100 cubic metres of waste daily.
To get the plant up to
par, the city would have to put another $3.3 million worth of work into it.
Council will have to vote
on whether to go with the engineers recommendations. The mayor said no
date for the vote has been set.
In 1997, after determining
the sewage lagoon wouldnt have the capacity to deal with waste produced
by the growing city, council hired Hill Murray and Associates to build a treatment
plant.
But the companys
work on the plant was flawed, causing leaks in the concrete tanks. The city
stopped construction and spent eight months repairing the damage.
Council then undertook
this major review of the plant, wanting to see if there was any way to breathe
life back into the failed project.
"I think the reality
is that well be using the sewage lagoon for another season," the
mayor said.
But hes confident
that Iqaluit residents will see the sewage plant up and running, possibly sometime
next year.
"Its right and
proper to treat the sewage with a way other than the sewage lagoon," Matthews
said. "Its definitely a priority, so were going to have to
come up with the money somehow to make it happen."
|